Louisiana joins four states in complaint against electricity grid operator

Spread the love

(The Center Square) – Louisiana and four other state public service commissions have filed a formal complaint against the Midcontinent Independent System Operator, accusing the grid operator of reliance on “patently unreasonable” assumptions to justify $22 billion worth of transmission projects in its long-range planning portfolio.

The grid operator functions to coordinate the reliable transmission of electricity across multiple states by managing power flows.

In a filing with the Federal Energy Regulatory Commission, the Louisiana Public Service Commission joined commissions from Arkansas, Mississippi, North Dakota and Montana in an accusation of a defective business case for the nonprofit’s Long Range Transmission projects known as Tranche 2.1.

Tranche 2.1, which only includes grid upgrades in the Midwest, will construct “a 3,631-mile 765 kV and 345 kV backbone that ensures future reliability while providing benefits that exceed costs,” according to the grid operator.

“The Louisiana Public Service Commission joined the complaint for two major reasons,” a spokesman for the commission wrote to The Center Square in an email. “First, MISO’s LRTP 2.1 process is flawed due to the unreasonable underlying assumptions relied upon to justify those projects as Multi Value Projects, which results in a broad allocation of costs. In addition, our concern is that, although currently there is no allocation of these costs to Louisiana, due to FERC precedent established in the Sunflower case, Louisiana is not guaranteed insulation from an allocation of those costs into the future.”

“These projects fail to meet the fundamental requirement of providing benefits equal to or in excess of forecasted costs,” the complaint says.

The complaint says the grid operator overstated economic benefits to push the portfolio’s benefit-to-cost ratio above the 1.0 threshold that is required.

The complaint asserts that the grid operator added new benefit metrics and revised others after its original modeling failed to show benefits exceeding costs. Stakeholders, including Midcontinent’s Independent Market Monitor, reportedly raised concerns about these assumptions throughout the stakeholder process, but the complaint says those were “ignored.”

“When the market monitor identified major defects with MISO’s assumptions, rather than address those concerns, MISO ordered staff to challenge the IMM’s authority,” the complaint states.

Potomac Economics, the market monitor, says the plan likely looks better on paper than in reality.

Potomac said Midcontinent made a couple of assumptions that don’t hold water, such as counting extra power plants that wouldn’t actually be needed and exaggerating the risk of blackouts, among others. Fixing those mistakes, the complaint argues, would show the plan’s costs outweigh its benefits.

Midcontinent, operating across parts of 15 states and the Canadian province of Manitoba, pushed back strongly against the allegations. The grid operator said the “deficient and misleading” complaint threatens to undermine needed infrastructure and inject regulatory uncertainty into future generation and transmission planning.

Jeremiah Doner, representing the grid operator, rejected the claim that Tranche 2.1 forces states to pay for unneeded projects, saying the plan was built in collaboration with state regulators and utilities and reflects their resource plans.

Doner said in his testimony that 93% of the generation in its “1A” planned infrastructure upgrades and more than half in “2A” came directly from member-submitted plans, with the rest added by the operator’s model to meet system needs.

“While the LRTP Tranche 2.1 Portfolio is estimated to cost MISO members about $5 per 1 MWh or 1,000 kWh of energy used, that investment will 12 provide $10 to $18 of value over that same amount of usage,” Midcontinent Independent System Operator said.

The long term planning effort is being rolled out in multiple tranches, with the first three focused on the Midwest region. Later tranches will address the South region and interconnections between the Midwest and South, where the nonprofit says transmission capacity is increasingly strained by a surge in renewable projects seeking interconnection.

The company’s South region includes Louisiana, Texas, Mississippi and Arkansas. The Central includes Illinois, Missouri, Kentucky, Indiana, Michigan and Wisconsin. The North includes Iowa, Minnesota, South Dakota, North Dakota, Montana and the Canadian province of Manitoba.

Leave a Comment





Latest News Stories

Platner leads Collins in Maine U.S. Senate race despite controversies

Platner leads Collins in Maine U.S. Senate race despite controversies

By Christen SmithThe Center Square Democrat and oyster farmer Graham Platner continues to out-poll incumbent Republican U.S. Sen. Susan Collins, despite mounting controversies about his treatment of women, fellow war...
Illinois quick hits: Illinois parole absconder arrested in Tennessee

Illinois quick hits: Illinois parole absconder arrested in Tennessee

By Jim Talamonti | The Center SquareThe Center Square Illinois parole absconder arrested in Tennessee The U.S. Marshals Service says an Illinois parole absconder has been captured in Union City,...
GOP rep: Time will tell on data center tax credit pause

GOP rep: Time will tell on data center tax credit pause

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – After Gov. J.B. Pritzker announced that his administration would pause data center tax credits, a Republican legislator...
Montana governor to Washington companies: We want your business

Montana governor to Washington companies: We want your business

By Carleen JohnsonThe Center Square The Governor of Montana tells The Center Square he hopes to lure more out of state business expansion into his state, following this week’s announcement...
WATCH: Civil rights curriculum aims to shape future leaders

WATCH: Civil rights curriculum aims to shape future leaders

By Esther WickhamThe Center Square It was the winter of 1962. Demonstrators in Birmingham, Alabama, came to see Dr. Martin Luther King Jr. for his support in organizing a protest...
Illinois officials say Bears still may stay despite team's Indiana statement

Illinois officials say Bears still may stay despite team’s Indiana statement

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Although the Chicago Bears say the team’s board of directors moved to advance plans for a stadium...
More than 60% of Minnesota high-risk Medicaid providers fail review

More than 60% of Minnesota high-risk Medicaid providers fail review

By Elyse ApelThe Center Square Nearly two-thirds of Minnesota's high-risk Medicaid providers have had taxpayer funding paused following a federally-mandated review process that state officials say was necessary to protect...
Senate sends $70B bill funding ICE, border patrol to vacant House

Senate sends $70B bill funding ICE, border patrol to vacant House

By Thérèse BoudreauxThe Center Square U.S. Senate Republicans finally passed their roughly $70 billion immigration enforcement funding bill after an 18-hour vote-a-rama that ended early Friday morning. The 52-47 final...
Chicago Bears to advance stadium project in Indiana

Chicago Bears to advance stadium project in Indiana

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Chicago Bears are moving forward with plans to build a stadium in Northwest Indiana. Bears Chairman...
Greer, Carr commended for seeking fairness in EU treatment of US tech firms

Greer, Carr commended for seeking fairness in EU treatment of US tech firms

By Tate RosentreterThe Center Square Public Policy Solutions sent a letter Friday to United States Trade Representative Ambassador Jamieson Greer and Federal Communications Commission chairman Brendan Carr commending both men...
Illinois quick hits: Pritzker pauses data center tax credits

Illinois quick hits: Pritzker pauses data center tax credits

By Jim Talamonti | The Center SquareThe Center Square Pritzker pauses data center tax credits Gov. J.B. Pritzker has ordered the Illinois Department of Commerce and Economic Opportunity to pause...
U.S. adds 172k jobs in 'strong' May report, unemployment remains at 4.3%

U.S. adds 172k jobs in ‘strong’ May report, unemployment remains at 4.3%

By Andrew RiceThe Center Square The U.S. economy added 172,000 jobs in May's better-than-expected report while the unemployment rate remained at 4.3%, according to data released Friday by the U.S....
Researchers put a number on how much debt U.S. can carry

Researchers put a number on how much debt U.S. can carry

By Brett RowlandThe Center Square The United States has about 20 years to change course on its national debt before it reaches the estimated limits of its debt capacity, according...
Colorado governor vetoes legislation allowing ICE to be sued

Colorado governor vetoes legislation allowing ICE to be sued

By Liam HibbertThe Center Square Colorado Gov. Jared Polis vetoed a Democrat-backed bill on Wednesday that would have allowed citizens to sue immigration enforcement officers for civil rights violations. The...
Ballots processed slowly as Californians await 36-day count

Ballots processed slowly as Californians await 36-day count

By Chris WoodwardThe Center Square It will be more than a month before Californians see the official results from Tuesday's primary. That is especially the case in the races for...