‘Consequential’ day ahead for future household electricity costs

Spread the love

(The Center Square) – PJM’s Board of Directors is preparing to make one of the most consequential decisions of this decade, says a coalition of state legislators from the grid operator’s region.

And, depending upon the choice made, it could save households and businesses as much as $70 per month on their utility bills.

On Monday, ahead of a pending Nov. 19 vote on proposals that would determine how data centers should be connected to the grid, the coalition announced it submitted a plan to ensure the 67 million Americans served by PJM will not bear an unfair share of reliability risk and cost driven by soaring data center electricity demand.

The Protecting Ratepayers Proposal came in response to PJM’s Critical Issues Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions on managing rapid growth of large load customers like data centers.

The proposal builds on a resolution passed by the National Conference of State Legislators and upon elements of others submitted to PJM, including one submitted by the governors of Maryland, Virginia, New Jersey, and Pennsylvania, in partnership with the Data Center Coalition and Exelon.

It also echoes proposals from consumer advocate groups in Pennsylvania and Maryland and has gained the support of the Natural Resources Defense Council, or NRDC, whose original suggestions were included.

During a media briefing on Monday, Democratic DC Councilmember Charles Allen emphasized that the issue impacts everyone, and the coalition’s size and scope highlight what’s at stake. “It’s not very often that leaders from a broad number of states come together in a shared fight,” he added.

Sen. Katie Fry Hester, D-Md., explained that anticipated demand from new data centers is projected to reach 32 GW, with some forecasts suggesting it could grow to 60 GW in the coming years.

“That’s the equivalent of adding a major city like Philadelphia to the grid almost overnight,” she said.

On Wednesday, after reviewing between 16 and 20 proposals, PJM and its members – including utility companies, transmission operators and power generators – then vote on their recommendations to the Board of Directors.

“Data centers should power their profits, not drain the wallets of everyday Americans,” said Sen. Rachel Ventura, a Democrat from Illinois.

Her state, she said, has already started to address the challenge by passing Senate Bill 25, also known as The Clean and Reliable Grid Affordability Act, now awaiting Gov. JB Pritzker’s signature.

The bill invests in battery storage, energy efficiency, and smart grid technologies, Ventura said. It adds 3 GW of storage with no upfront cost to consumers, which can be dispatched at peak time to lower prices and improve reliability. She noted that it’s a strong first step, but Illinois alone cannot solve a regional problem.

“The cost of electricity is expected to skyrocket by over $100 billion through 2033 due to data center load growth, which could cost families and businesses in PJM territory an extra $70 per month,” said Claire Lang-Ree, advocate for the Sustainable FERC Project at NRDC.

Lang-Ree said the coalition’s proposal is one of the few that addresses the difficult question of what happens if there isn’t enough power to go around.

She explained that under their proposal, data centers can join PJM quickly, but they will be interruptible – or the first to be curtailed – unless they bring their own capacity to the grid.

Other key features of the proposal include:

Multiple fast-track options for data centers to bring their own firm power supply through new power plants, demand response, or distributed resources – while preventing them from pulling existing plants from the grid or jumping ahead of renewable projects already in the queue. Load forecasting enhancements to screen out speculative projects for transmission planning.A temporary extension of the capacity market “price collar” to curb further price spikes.

Legislators stressed that while each state faces unique energy challenges, they are united in the shared goal of ensuring ratepayers across the PJM region are not subsidizing the energy costs of new data centers being built by Fortune 500 companies like Google, Amazon, and Microsoft.

Delaware and Maryland have enacted transparency laws requiring public utilities to report how they vote in the PJM Interconnection stakeholder/committee process, according to Sen. Stephanie Hansen, a Democrat from Delaware.

Energy resources are scarce, so competition is fierce, Hansen said.

“It’s the wild wild west when it comes to where data centers will be located. There are few rules, and states are competing against each other for jobs and revenue, “knowing that the cost to feed the energy monster,” as Hansen described it, “will be socialized to other ratepayers in and out of the state.”

She said they encourage PJM to forge a responsible path going forward – and keeping renewable projects at the forefront of interconnection planning is critically important. “This is a marathon, not a sprint,” she said, “and the starting gun has already sounded.”

Leave a Comment





Latest News Stories

Medical device manufacturer invests $110M to expand Nebraska plant, boost drug supply

Medical device manufacturer invests $110M to expand Nebraska plant, boost drug supply

By Tom JoyceThe Center Square A major American medical device manufacturer is investing $110 million to expand production in Nebraska as part of an effort to restore pharmaceutical manufacturing and...
Chicago council considers 'not a tax' surcharge on hotels

Chicago council considers ‘not a tax’ surcharge on hotels

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Chicago’s city council is considering a new assessment on hotel stays that supporters say would raise about...

IL Senate GOP: Pritzker, not Trump, raised power bills

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Senate Republicans say Gov. J.B. Pritzker is wrong to blame President Donald Trump for high electric...
SC weighs whether Amazon must pay workers for mandatory COVID screenings

SC weighs whether Amazon must pay workers for mandatory COVID screenings

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The Illinois Supreme Court is considering whether Amazon must compensate warehouse workers for time spent waiting...
WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

WATCH: Tax increase talk at Statehouse; Bost’s election lawsuit against Illinois wins standing

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop discusses the status of...
Illinois Quick Hits: Indiana governor 'working hard' to attract Bears

Illinois Quick Hits: Indiana governor ‘working hard’ to attract Bears

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Indiana Gov. Mike Braun says the Chicago Bears noticed that the Hoosier state is open for business....
Vance's tie-breaking vote tanks resolution restricting Venezuela military actions

Vance’s tie-breaking vote tanks resolution restricting Venezuela military actions

By Thérèse BoudreauxThe Center Square By the slimmest of margins, the U.S. Senate successfully derailed a resolution that would have curtailed the Trump administration’s power to continue military action in...
Federal court upholds California congressional redistricting

Federal court upholds California congressional redistricting

By Dave MasonThe Center Square California’s congressional redistricting, designed to pick up five more Democratic seats in this year’s midterm elections, was upheld Wednesday in a federal court in downtown...
Trump orders new mediation for New York rail contract dispute

Trump orders new mediation for New York rail contract dispute

By Chris Wade contributionThe Center Square President Donald Trump on Wednesday ordered new mediation for stalled contract talks between New York's Metropolitan Transportation Authority and union leaders in a last-ditch...
U.S. House passes two more govt funding bills, sending to Senate

U.S. House passes two more govt funding bills, sending to Senate

By Thérèse BoudreauxThe Center Square In a bipartisan vote Wednesday, the U.S. House passed a minibus containing two more full-year federal funding bills, sending the package to the Senate for...
Governors seek delay on sharing cost of food stamp errors

Governors seek delay on sharing cost of food stamp errors

By Brett RowlandThe Center Square State and local officials are asking Congress for a delay on sharing the cost of errors in the federal food assistance program, but said they...
Supreme Court ruling allows Bost to challenge Illinois election law

Supreme Court ruling allows Bost to challenge Illinois election law

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A U.S. Supreme Court ruling clears the way for U.S. Rep. Mike Bost to challenge Illinois’...
Illinois quick hits: Illinois auto insurance rates dropping

Illinois quick hits: Illinois auto insurance rates dropping

By Jim Talamonti | The Center SquareThe Center Square Illinois auto insurance rates dropping A new report says Illinois auto insurers are lowering premiums by 4.26% in 2026 while providers...
SCOTUS rules on warrantless searches, double convictions and election suits

SCOTUS rules on warrantless searches, double convictions and election suits

By Andrew RiceThe Center Square The U.S. Supreme Court decided three cases Wednesday about political candidates' standing to sue, warrantless searches, and double convictions. The justices marked Jan. 14 as...

WATCH: WA Democrats criticize reporter probes into potential daycare fraud

By Carleen JohnsonThe Center Square Washington state Democratic leaders responded fiercely to the notion of journalists looking into possible fraud regarding Washington state daycares that receive taxpayer funds. The issue...