Lake Land Trustees Approve Performance Contract for $4 Million Library Overhaul

Spread the love

Lake Land College Board of Trustees Meeting | May 11, 2026

Article Summary: The Lake Land College Board of Trustees approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, capped at $400,000, to manage a planned $4 million HVAC replacement and remodel of the Judge Learning Resource Center.

Learning Resource Center Project Key Points:

  • The board’s approval covers Omni Energy Partners’ fee of 10% of actual project cost, not to exceed $400,000; the total project budget is anticipated at $4 million.
  • The library’s HVAC system has multiple failures and is described as in dire need of replacement; potential federal tax credits of $300,000 to $500,000 could offset the HVAC portion.
  • Construction is scheduled to begin in spring 2027 and finish in fall 2027, with all future work bid through the college’s normal process and brought back to the board.
  • The project will be funded through a combination of fund balance and public health safety funds.

MATTOON — The Lake Land College Board of Trustees on Monday, May 11, 2026, approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, for an amount not to exceed $400,000, setting in motion a planned $4 million HVAC replacement and remodel of the college’s Judge Learning Resource Center, the campus library.

Vice President for Business Services John Woodruff presented the item, which trustees passed unanimously on a roll-call vote, 7-0, with Student Trustee Wyatt Draper absent. Trustee Larry Lilly moved approval and Trustee Gary Cadwell seconded.

According to Woodruff’s memo in the board packet, the library’s HVAC system “has multiple failures and is in dire need of replacement,” and the replacement would qualify for potential tax credits under Section 48 of the Internal Revenue Code. The remodel work covers the IT area and the main and second floors, with the main-floor remodel aimed at enhancing student use. The library remodel is on the college’s Master Facility plan, and the college plans to solicit student feedback as part of the remodel effort.

Two Proposals, Scored by Rubric

Rather than a traditional architecture engagement, the college used a performance-contract approach. The request for proposals was advertised in major in-district daily newspapers and on the college’s facilities website, with specifications mailed to area contractors. Two proposals were received, from Omni Energy Partners and Veregy, Inc. The facilities team met with each vendor for an hour, asked questions about key attributes of the proposals, and then scored each vendor using a rubric based on proposed solutions and related costs. The team recommended Omni Energy Partners.

Under the agreement, Omni charges 10% of the actual project cost rather than projected cost, a structure Woodruff told the board potentially offers savings. With an anticipated $4 million budget, payments would total approximately $400,000. On the remodel portion, the college expects to recognize savings versus a traditional architect, and the HVAC portion would be offset by potential tax credits of $300,000 to $500,000 that Omni can navigate on the college’s behalf.

The remodel’s preliminary design creates more group study opportunities for students and an active connection to the Luther Student Center, including a door connecting the student center to the Learning Resource Center.

Contract Terms

The master agreement included in the packet identifies the contractor as Omni Energy Partners, LLC, a Missouri corporation at 214 Villa Drive, Lake St. Louis. Its printed terms require a performance and payment bond equal to the contract price before work begins, compliance with the Illinois Prevailing Wage Act, criminal background checks for all workers on site, monthly progress invoicing at net 30 days, and a mobilization fee of 15% of the contract price due at contract execution. The agreement’s energy guarantee attachment states a term of 20 years from final project acceptance, with utility rates escalated at not less than 3% annually for savings calculations. Key financial fields in the packet version of the agreement — including the contract price and the savings schedule — are blank pending execution.

All future bids for the HVAC and remodel work will go through the college’s normal bid process, with recommendations submitted to the board for approval.

Leave a Comment





Latest News Stories

Screenshot 2025-12-24 at 1.11.08 PM

Police Department Adds New Officer, Introduces Another

Casey City Council Meeting | December 15, 2025 Article Summary: The City Council approved the hiring of Daniel Martinez to fill the police department's ninth position and formally welcomed recently...
Meeting Briefs

Meeting Summary and Briefs: Casey Township Library Board for Nov. 2025

Casey Township Library Board Meeting | Nov. 2025 The Casey Township Library Board convened twice in November 2025 to manage regular business and advance a major building expansion project. During...
lake land college.4

Lake Land College Board Awards $2.5 Million Contract for Front Entrance Improvements

Lake Land College Board of Trustees Meeting | November 2025 Article Summary: The Lake Land College Board of Trustees approved a multi-million dollar contract to overhaul the campus entrances, including...
Clark County Graphic.4

County Board Approves Proposal for New Rural-Focused Ambulance Support

Clark County Board Regular Meeting | November 2025 Article Summary: The Clark County Board authorized a proposal from H&H EMS Solutions to provide support services for the county's ambulance operations,...
Meeting Briefs

Meeting Summary and Briefs: Casey-Westfield CUSD C-4 Board for December 15, 2025

Casey-Westfield CUSD C-4 Board Meeting | December 15, 2025 The Casey-Westfield Community Unit School District C-4 Board of Education met on Monday, December 15, 2025, to address financial planning and...
Screenshot 2025-12-24 at 1.11.27 PM

Council Hires EJ Water for Certified Operator Services

Casey City Council Meeting | December 15, 2025 Article Summary: The Council approved agreements with EJ Water to provide certified oversight for the city's water and wastewater systems while the...
Casey Library.3

Library Highlights Fundraising Success and Holiday Event Plans

Casey Township Library Board Meeting | Nov. 2025 Article Summary: The Casey Township Library Board received updates on recent fundraising efforts and youth programming participation. Officials noted the receipt of...
Clark County Graphic.6

Clark County Board Adopts Fiscal Year 2026 Budget and Tax Levies

Clark County Board Regular Meeting | November 2025 Article Summary: The Clark County Board formally approved the county's operating budget for the 2026 fiscal year and adopted a comprehensive series...
Casey Westfield School Board.3

Casey-Westfield Students Earn Drone Certifications and Ag Awards; Elementary Raises $6,500

Casey-Westfield CUSD C-4 Board Meeting | December 15, 2025 Article Summary: Administrator reports presented to the School Board highlighted hands-on learning achievements, including drone certifications for aerospace students and top...
At right, Lake Land College President Josh Bullock recognizes Brandon Miller, Casey, as a nominee for the 2025 Lake Land College Non-Traditional Student of the Year award during the College’s annual Non-Traditional Student of the Year ceremony.

Lake Land Honors Casey Non-Traditional Student of the Year Nominees

Featured Photo Caption: At right, Lake Land College President Josh Bullock recognizes Brandon Miller, Casey, as a nominee for the 2025 Lake Land College Non-Traditional Student of the Year award...
Screenshot 2025-12-24 at 1.11.19 PM

Superintendent Shelby Biggs Retires After Three Decades

Casey City Council Meeting | December 15, 2025 Article Summary: Longtime Utility Superintendent Shelby Biggs attended his final City Council meeting as an official employee, receiving praise and well-wishes from...
Casey illinois library.1.logo graphic

Casey Library Board Advances Expansion Plans, Selects Ramp Design

Casey Township Library Board Meeting | Nov. 2025 Article Summary: The Casey Township Library Board moved forward with plans for a building addition, holding a special meeting to address specific...
solar panels photovoltaics in solar farm

Clark County Board Approves $4.8 Million Solar Road Agreement, Weighs New State Energy Rules

November Special Board Meeting Article Summary: The Clark County Board approved a major road use agreement for the Moonshine Solar Project, securing millions for infrastructure improvements in Johnson Township. The...
Casey Westfield School Board.2

District Approves $1.4 Million Lease Agreement for Nine New School Buses

Casey-Westfield CUSD C-4 Board Meeting | December 15, 2025 Article Summary: The Casey-Westfield School Board approved a five-year lease and purchase agreement to update its transportation fleet with new vehicles....
Screenshot 2025-12-24 at 1.11.08 PM

Casey City Council Approves Utility Fee Increases

Casey City Council Meeting | December 15, 2025 Article Summary: The City Council voted unanimously to update the city’s code of ordinances regarding utility disconnection and reconnection fees, doubling the...