Lake Land Trustees Approve Performance Contract for $4 Million Library Overhaul

Spread the love

Lake Land College Board of Trustees Meeting | May 11, 2026

Article Summary: The Lake Land College Board of Trustees approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, capped at $400,000, to manage a planned $4 million HVAC replacement and remodel of the Judge Learning Resource Center.

Learning Resource Center Project Key Points:

  • The board’s approval covers Omni Energy Partners’ fee of 10% of actual project cost, not to exceed $400,000; the total project budget is anticipated at $4 million.
  • The library’s HVAC system has multiple failures and is described as in dire need of replacement; potential federal tax credits of $300,000 to $500,000 could offset the HVAC portion.
  • Construction is scheduled to begin in spring 2027 and finish in fall 2027, with all future work bid through the college’s normal process and brought back to the board.
  • The project will be funded through a combination of fund balance and public health safety funds.

MATTOON — The Lake Land College Board of Trustees on Monday, May 11, 2026, approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, for an amount not to exceed $400,000, setting in motion a planned $4 million HVAC replacement and remodel of the college’s Judge Learning Resource Center, the campus library.

Vice President for Business Services John Woodruff presented the item, which trustees passed unanimously on a roll-call vote, 7-0, with Student Trustee Wyatt Draper absent. Trustee Larry Lilly moved approval and Trustee Gary Cadwell seconded.

According to Woodruff’s memo in the board packet, the library’s HVAC system “has multiple failures and is in dire need of replacement,” and the replacement would qualify for potential tax credits under Section 48 of the Internal Revenue Code. The remodel work covers the IT area and the main and second floors, with the main-floor remodel aimed at enhancing student use. The library remodel is on the college’s Master Facility plan, and the college plans to solicit student feedback as part of the remodel effort.

Two Proposals, Scored by Rubric

Rather than a traditional architecture engagement, the college used a performance-contract approach. The request for proposals was advertised in major in-district daily newspapers and on the college’s facilities website, with specifications mailed to area contractors. Two proposals were received, from Omni Energy Partners and Veregy, Inc. The facilities team met with each vendor for an hour, asked questions about key attributes of the proposals, and then scored each vendor using a rubric based on proposed solutions and related costs. The team recommended Omni Energy Partners.

Under the agreement, Omni charges 10% of the actual project cost rather than projected cost, a structure Woodruff told the board potentially offers savings. With an anticipated $4 million budget, payments would total approximately $400,000. On the remodel portion, the college expects to recognize savings versus a traditional architect, and the HVAC portion would be offset by potential tax credits of $300,000 to $500,000 that Omni can navigate on the college’s behalf.

The remodel’s preliminary design creates more group study opportunities for students and an active connection to the Luther Student Center, including a door connecting the student center to the Learning Resource Center.

Contract Terms

The master agreement included in the packet identifies the contractor as Omni Energy Partners, LLC, a Missouri corporation at 214 Villa Drive, Lake St. Louis. Its printed terms require a performance and payment bond equal to the contract price before work begins, compliance with the Illinois Prevailing Wage Act, criminal background checks for all workers on site, monthly progress invoicing at net 30 days, and a mobilization fee of 15% of the contract price due at contract execution. The agreement’s energy guarantee attachment states a term of 20 years from final project acceptance, with utility rates escalated at not less than 3% annually for savings calculations. Key financial fields in the packet version of the agreement — including the contract price and the savings schedule — are blank pending execution.

All future bids for the HVAC and remodel work will go through the college’s normal bid process, with recommendations submitted to the board for approval.

Leave a Comment





Latest News Stories

Casey Council Meeting Graphic.2

Casey City Council Awards Sidewalk Contract, Approves Utility Rate Increases

The Casey City Council unanimously approved awarding a $62,502 sidewalk construction contract to Wallace Concrete at Monday's meeting, accepting the low bid from among several proposals reviewed by city staff....
Casey Council Meeting Graphic.1

Utilities Chief Announces December Retirement; Police Department Adds Officer

Casey Utility Superintendent Shelby Biggs announced at Monday's city council meeting that he will retire on December 31, 2025, ending his tenure overseeing the city's water, sewer, and electric operations....
City Council Meeting Briefs.Purple

Casey Council Meeting Briefs

July 4th Planning Begins: City Clerk Jeremy Mumford reminded the council that planning for the 4th of July celebration needs to begin soon. Mayor Mike Nichols asked the Downtown Improvement/Festivals...
Casey Westfield School Board.1

Casey-Westfield Board Approves Major Technology Upgrades, Facility Improvements

The Casey-Westfield School Board approved significant technology and facility upgrades totaling more than $76,000 during Monday's meeting, while also addressing multiple personnel changes as the district prepares for summer construction...
Casey Westfield School Board.2

Casey-Westfield Students Excel in Academics and Community Service

Casey-Westfield students demonstrated exceptional achievement across multiple areas while participating in unique educational experiences and community service initiatives, according to administrator reports from Monday's board meeting. High school students received...
Casey Westfield School Board.3

SCHOOL BOARD MEETING BRIEFS

Summer Construction Planned: Major facility improvements begin after Memorial Day, with cafeterias closed June 2-17 for asbestos abatement and Agriculture/Industrial Arts Building without power for electrical upgrades. State Track Qualifiers:...
Casey Westfield School Board.2

Casey-Westfield School Board Reorganizes Leadership, Seats New Member

The Casey-Westfield School Board completed its post-election reorganization Monday evening, maintaining current leadership while welcoming new member Mike Fouty and establishing committee assignments for the coming term. The organizational meeting...
Casey Westfield School Board.3

SCHOOL BOARD BRIEFS

Election Results Certified: The April 1 school board election results were officially certified, with Mike Fouty joining as the new member after receiving 282 votes for a four-year term. Leadership...
Casey Council Meeting Graphic.1

Casey Completes $498,279 Housing Rehabilitation Grant Project

The City of Casey successfully completed a nearly half-million dollar housing rehabilitation program that brought nine homes up to code and assisted 19 low-to-moderate income residents, officials announced during a...
City Council Meeting Briefs.Blue

CITY MEETING BRIEFS

Grant Administration Success: The Coles County Regional Planning & Development Commission successfully administered the $498,279 housing rehabilitation grant with 100% of funds reaching qualifying low-to-moderate income households. No Resident Displacement:...
Casey Westfield School Board.3

Casey-Westfield Board Approves $100,000+ in Technology and Facility Upgrades

The Casey-Westfield School Board approved more than $100,000 in technology purchases and facility improvements during Monday's meeting, while also addressing administrative cost limitations and preparing for new board member transitions....
Casey Westfield School Board.1

Casey-Westfield Students Excel in Academics and Community Service

Casey-Westfield students demonstrated exceptional achievement across academic competitions, community service, and educational experiences, according to administrator reports presented during Monday's board meeting. High school students showcased academic excellence through multiple...
Casey Westfield School Board.2

SCHOOL BOARD MEETING BRIEFS

Bond Funds Secured: The Series 2025 HLS Bonds closed April 15 with proceeds deposited at Casey State Bank and fully collateralized, advancing facility improvement projects. Board Transition Pending: New board...
Casey Council Meeting Graphic.1

Casey Council Approves Major Equipment Purchase, Awards Tree Removal Contracts

The Casey City Council authorized the purchase of a $191,537.50 hydro-vac truck and awarded contracts totaling more than $40,000 for tree and stump removal projects during Monday's meeting, while also...
Casey Council Meeting Graphic.2

Casey Committee Maintains Chicken Ban, Advances Planning Initiatives

Casey city committees addressed livestock regulations and economic development planning during meetings held before Monday's council session, with decisions that will affect both residential regulations and long-term community growth. The...