Lake Land Trustees Approve Performance Contract for $4 Million Library Overhaul

Spread the love

Lake Land College Board of Trustees Meeting | May 11, 2026

Article Summary: The Lake Land College Board of Trustees approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, capped at $400,000, to manage a planned $4 million HVAC replacement and remodel of the Judge Learning Resource Center.

Learning Resource Center Project Key Points:

  • The board’s approval covers Omni Energy Partners’ fee of 10% of actual project cost, not to exceed $400,000; the total project budget is anticipated at $4 million.
  • The library’s HVAC system has multiple failures and is described as in dire need of replacement; potential federal tax credits of $300,000 to $500,000 could offset the HVAC portion.
  • Construction is scheduled to begin in spring 2027 and finish in fall 2027, with all future work bid through the college’s normal process and brought back to the board.
  • The project will be funded through a combination of fund balance and public health safety funds.

MATTOON — The Lake Land College Board of Trustees on Monday, May 11, 2026, approved a performance agreement with Omni Energy Partners of Lake St. Louis, Missouri, for an amount not to exceed $400,000, setting in motion a planned $4 million HVAC replacement and remodel of the college’s Judge Learning Resource Center, the campus library.

Vice President for Business Services John Woodruff presented the item, which trustees passed unanimously on a roll-call vote, 7-0, with Student Trustee Wyatt Draper absent. Trustee Larry Lilly moved approval and Trustee Gary Cadwell seconded.

According to Woodruff’s memo in the board packet, the library’s HVAC system “has multiple failures and is in dire need of replacement,” and the replacement would qualify for potential tax credits under Section 48 of the Internal Revenue Code. The remodel work covers the IT area and the main and second floors, with the main-floor remodel aimed at enhancing student use. The library remodel is on the college’s Master Facility plan, and the college plans to solicit student feedback as part of the remodel effort.

Two Proposals, Scored by Rubric

Rather than a traditional architecture engagement, the college used a performance-contract approach. The request for proposals was advertised in major in-district daily newspapers and on the college’s facilities website, with specifications mailed to area contractors. Two proposals were received, from Omni Energy Partners and Veregy, Inc. The facilities team met with each vendor for an hour, asked questions about key attributes of the proposals, and then scored each vendor using a rubric based on proposed solutions and related costs. The team recommended Omni Energy Partners.

Under the agreement, Omni charges 10% of the actual project cost rather than projected cost, a structure Woodruff told the board potentially offers savings. With an anticipated $4 million budget, payments would total approximately $400,000. On the remodel portion, the college expects to recognize savings versus a traditional architect, and the HVAC portion would be offset by potential tax credits of $300,000 to $500,000 that Omni can navigate on the college’s behalf.

The remodel’s preliminary design creates more group study opportunities for students and an active connection to the Luther Student Center, including a door connecting the student center to the Learning Resource Center.

Contract Terms

The master agreement included in the packet identifies the contractor as Omni Energy Partners, LLC, a Missouri corporation at 214 Villa Drive, Lake St. Louis. Its printed terms require a performance and payment bond equal to the contract price before work begins, compliance with the Illinois Prevailing Wage Act, criminal background checks for all workers on site, monthly progress invoicing at net 30 days, and a mobilization fee of 15% of the contract price due at contract execution. The agreement’s energy guarantee attachment states a term of 20 years from final project acceptance, with utility rates escalated at not less than 3% annually for savings calculations. Key financial fields in the packet version of the agreement — including the contract price and the savings schedule — are blank pending execution.

All future bids for the HVAC and remodel work will go through the college’s normal bid process, with recommendations submitted to the board for approval.

Leave a Comment





Latest News Stories

U.S. Senate race headlines Maine primaries as voters head to polls Tuesday

U.S. Senate race headlines Maine primaries as voters head to polls Tuesday

By Andrew RiceThe Center Square Voters in Maine will head to the polls Tuesday in high profile primary races that could help determine control of Congress. The races have garnered...
Bessent backs 3% deficit goal despite 5% budget forecasts

Bessent backs 3% deficit goal despite 5% budget forecasts

By Brett RowlandThe Center Square U.S. Treasury Secretary Scott Bessent pledged in two congressional hearings this week to cut the federal deficit to 3% of GDP, a target the government's...
Constables hope to find missing children in immigration search effort

Constables hope to find missing children in immigration search effort

By Bethany BlankleyThe Center Square After months of Congress stalling on funding for U.S. Immigration and Customs Enforcement and administrative changes, Pennsylvania state constables who’ve signed agreements to support federal...
Lawmaker blasts reports of ‘equitable assessments’ at medical school

Lawmaker blasts reports of ‘equitable assessments’ at medical school

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois State Rep. Bill Hauter, a Republican physician and graduate of the University of Illinois College...
FOID changes advance in Illinois House, not called in Senate

FOID changes advance in Illinois House, not called in Senate

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Changes to Illinois’ Firearm Owner’s ID Card didn’t get across the finish line before the General Assembly...
Texas tops California, New York, with the most Fortune 500 headquarters

Texas tops California, New York, with the most Fortune 500 headquarters

By Bethany BlankleyThe Center Square Under Gov. Greg Abbott, the most Fortune 500 headquarters are now located in Texas. According to Fortune Media’s 2026 Fortune 500 list, its top companies...
Nine candidates run in Las Vegas congressional district

Nine candidates run in Las Vegas congressional district

By Liam HibbertThe Center Square Nevada’s 1st Congressional district sees a total of nine candidates vying for Tuesday's Democratic and Republican primaries, but only two have captured the majority of...
U.S. seeks dismissal of lawsuit over deadly boat strikes

U.S. seeks dismissal of lawsuit over deadly boat strikes

By Brett RowlandThe Center Square The U.S. government moved Friday to dismiss a lawsuit brought by families of two Trinidadian men killed in a U.S. military boat strike, arguing the...
Seattle mayor reverses course, activates surveillance cameras for World Cup

Seattle mayor reverses course, activates surveillance cameras for World Cup

By Randy DiamondThe Center Square In a reversal, Seattle Mayor Katie Wilson has ordered that surveillance cameras be turned on during the FIFA World Cup Tournament. Wilson said in a...
Chicago judge sides against Florida attorney general on kids transgender medicine

Chicago judge sides against Florida attorney general on kids transgender medicine

By Scott Holland | Legal NewslineThe Center Square A federal judge in Chicago has refused to dismiss a lawsuit the American Academy of Pediatrics lodged against Florida Attorney General James...
Expert: GOP success this week doesn't mean Nov. 3 victories

Expert: GOP success this week doesn’t mean Nov. 3 victories

By Chris WoodwardThe Center Square Republicans appear to have done well in this week's California primary, despite Democrats redrawing congressional districts in their favor. But an expert observing Tuesday's election...
High-speed rail project criticized again after $3.5B contract

High-speed rail project criticized again after $3.5B contract

By Madeline ShannonThe Center Square After a $3.5 billion contract was awarded for track and electrical work on California’s high-speed rail, critics are calling the entire project problematic because of...
Platner leads Collins in Maine U.S. Senate race despite controversies

Platner leads Collins in Maine U.S. Senate race despite controversies

By Christen SmithThe Center Square Democrat and oyster farmer Graham Platner continues to out-poll incumbent Republican U.S. Sen. Susan Collins, despite mounting controversies about his treatment of women, fellow war...
Illinois quick hits: Illinois parole absconder arrested in Tennessee

Illinois quick hits: Illinois parole absconder arrested in Tennessee

By Jim Talamonti | The Center SquareThe Center Square Illinois parole absconder arrested in Tennessee The U.S. Marshals Service says an Illinois parole absconder has been captured in Union City,...
GOP rep: Time will tell on data center tax credit pause

GOP rep: Time will tell on data center tax credit pause

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – After Gov. J.B. Pritzker announced that his administration would pause data center tax credits, a Republican legislator...