Casey Awards $917,745 Contract for I-70 Sewer and Water Extension

Spread the love

Casey City Council Meeting | July 6, 2026

Article Summary: The Casey City Council unanimously awarded a $917,745.12 contract to B&T Drainage Inc. for the sewer and water portion of the I-70 and Illinois Route 49 interchange utility extension, roughly $157,000 under the engineer’s estimate.

I-70 Utility Extension Key Points:

  • B&T Drainage Inc. submitted the low bid of $917,745.12, well below HWC Engineering’s $1,074,700 estimate; the only other bid, from Dashiell Contracting Inc., came in at $1,314,421.
  • The project includes a new water main under Illinois Route 49, gravity sanitary sewer, a new duplex submersible lift station and a sanitary force main drilled under Interstate 70.
  • Director of Public Works Ryan Staley said earlier boring work at the interchange has gone smoothly and B&T will next assist with the electric portion along the interstate right-of-way.
  • Contract signing and the bond process begin immediately following Monday’s approval.

CASEY — The Casey City Council on Monday, July 6, 2026, unanimously approved Resolution #070626A, awarding a $917,745.12 construction contract to B&T Drainage Inc. for the sewer and water phase of the city’s utility extension to the Interstate 70 and Illinois Route 49 interchange.

Director of Public Works Ryan Staley told the council the work went out to bid and B&T Drainage was the apparent low bidder. “It was a complete bid, and HWC, the engineers of record, and myself both recommend the approval of that work,” Staley said. Alderman Steve Jenkins made the motion to approve, and the roll call passed unanimously.

According to a bid review letter from HWC Engineering project manager Steven J. Shannon, two bids were opened June 17, 2026. B&T Drainage’s $917,745.12 unit-price bid was complete and conformed with bidding requirements, while Dashiell Contracting Inc. bid $1,314,421. The engineer’s estimate for the work was $1,074,700, meaning the winning bid came in about 15 percent below projections. HWC recommended the award contingent on funding and legal review.

What the Project Builds

The contract covers extension of a 6-inch water main underneath Route 49, installation of 8-inch gravity sanitary sewer, a new duplex submersible lift station, and a 4-inch sanitary force main installed by directional drill underneath I-70. The force main will discharge into an existing manhole adjacent to the McDonald’s drive, and the contract includes all electrical work and controls at the new lift station. The largest line items in B&T’s certified bid tabulation include $255,005 for the lift station, $193,182 for pump controls and electrical, and $91,728 to directionally drill the force main under the interstate inside a 12-inch casing.

“After it’s approved tonight, we get it signed and I’ll start the contracts and bond process,” Staley said.

The award is the second major piece of the interchange utility push handed to B&T Drainage, which received the utility line extension boring contract under Resolution #060126B at the council’s June 1 meeting. Staley reported that the earlier boring work is essentially complete underneath I-70 and Route 49 and north of the McDonald’s area, and that B&T will now help the city with the electric portion of the extension along the interstate right-of-way.

“Everything’s going really smoothly with that so far,” Staley said. “We’ve been thrilled — they’ve done a really good job for us.”

The city’s newly adopted fiscal year 2027 appropriations ordinance carries I-70 project lines across four utility funds — $1,875,000 in the sewer fund, $312,500 in electric, $250,000 in gas and $87,500 in water — reflecting the scale of the interchange buildout, which city officials view as groundwork for development at the city’s I-70 gateway.

Leave a Comment





Latest News Stories

Spittler-Excavating-LLC-5-1

Spittler Excavating LLC

Welcome to Spittler Excavating LLC, a trusted leader in excavation services, committed to delivering superior quality and exceptional customer satisfaction. With years of industry expertise, we specialize in a comprehensive...
Special-Delivery-by-Kims-Crafts-4

Special Delivery by Kim’s Crafts

Special Delivery by Kim's Crafts is a premier destination for handcrafted, personalized gifts and unique creations. Located in the heart of Casey, Illinois, at 16 E. Main St., our shop...
Shore-Murphy-Associates-of-Casey-4

Shore-Murphy & Associates of Casey

Welcome to Shore-Murphy & Associates Of Casey, where we provide expert accounting and financial services tailored to meet the unique needs of our clients. Located at 508 N. Route 49,...
Shoaff-Law-LLC-4

Shoaff Law LLC

Shoaff Law LLC Shoaff Law LLC, located at 11 E. Main St., Casey, IL 62420, is dedicated to providing comprehensive legal services with a focus on client satisfaction and effective...
Sarah-Bush-Lincoln-Casey-Clinic-4

Sarah Bush Lincoln Casey Clinic

Sarah Bush Lincoln Casey Clinic is dedicated to delivering comprehensive, high-quality healthcare to the Casey, Illinois community and surrounding areas. As a part of the Sarah Bush Lincoln Health System,...
Richards-Farm-Restaurant-4

Richards Farm Restaurant

Founded in 1972, Richards Farm Restaurant is a cornerstone of Casey, Illinois, blending culinary excellence with rustic charm. Situated in a historic building that dates back to the 1930s, the...
Reflections-Family-Restaurant-4

Reflections Family Restaurant

Welcome to Reflections Family Restaurant, located at 15 South Central Ave., Casey, IL. Since opening our doors in 2000, we have been dedicated to providing our customers with the finest...

Big Things Attractions

Certified World's Largest: In Historic Downtown Casey, Illinois: World’s Largest Wind Chime (right beside the Whitling Whimsy Café at 109 E. Main St) World’s Largest Rocking Chair (across...
commercial-Garbage-service-IL413

Trash Pick a Day Late

City Hall will be closed Monday, September 2nd in observance of Labor Day. Also, trash will be picked up Tuesday, September 3rd instead of Monday, September 2nd. Have a great...
Candy-Canes-on-main-024

Main Street Closed for Candy Canes on Main

Main Street will be closed in December for Candy Canes on Main

Candy Canes On Main Dec 6 & 7, 2024

Candy Canes On Main December 6 @ 6:30 pm December 7 9 am - 4 pm CANDY CANES ON MAIN INVITES YOU TO JOIN US!! Experience a Home Town Christmas...

Casey Popcorn Festival

The Casey Popcorn Festival has run over the Labor Day weekend since 1987. Held at the 40-acre Fairview Park in Casey, IL, the popcorn festival features three full days of...
img_5036-scaled-1

Casey Softball Museum

The History of the Casey Softball Hall of Honor Original Museum The Casey Softball Hall of Honor & Museum was a brainchild of Trustees, LeRoy Staley, Joe Snedeker and Moe...