‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

Lake Land College.6

Foundation Announces Major Estate Gift; Board Accepts Workforce Grants

Lake Land College Board of Trustees Meeting | November 2025 Article Summary: The Lake Land College Foundation received a significant estate gift to support Mattoon students, while the board accepted...
Screenshot 2026-01-06 at 1.59.59 PM

Council Updates Security Light Fees; Installation Cost Set at $350

Meeting Summary and Briefs: City of Casey Council Meeting | Jan. 5, 2026 Article Summary: The City Council approved a new fee structure for private security lights installed on city...
Rotary Patty Richards

Patty Richards Guest Speaker at Rotary

Patty Richards (right) was the guest of Rotarian Marcy Mumford (left) at Tuesday’s weekly Rotary Club meeting at Richards Farm, discussing the Quincentennial--250 years celebration. The local theme will incorporate...
Screenshot 2026-01-06 at 1.59.48 PM

Casey Council Bans New Private Water Wells City-Wide

Meeting Summary and Briefs: City of Casey Council Meeting | Jan. 5, 2026 Article Summary: The Casey City Council has unanimously approved an ordinance prohibiting the installation or use of...
lake land college.1

College Offers Temporary Kitchen Lease to Deb’s Catering Following Fire

Lake Land College Board of Trustees Meeting | November 2025 Article Summary: To support a local business and community services after a fire, the board approved a temporary lease allowing...
Meeting Briefs

Meeting Summary and Briefs: Clark County Board for November 2025

Clark County Board Regular Meeting | November 2025 The Clark County Board met on Friday, November 21, 2025, to finalize the county's financial plans for the upcoming year. The primary...
Clark County Graphic.6

County Highway Department Secures Funding for Hogue Town Project, Completes Building Upgrades

Clark County Board Regular Meeting | November 2025 Article Summary: County Engineer Dallas Richardson reported on the approval of state funding for road work, the completion of a new facility,...
Meeting Briefs

Meeting Summary and Briefs: Casey City Council for December 15, 2025

Casey City Council Meeting | December 15, 2025 The Casey City Council met for its regular meeting on Monday, December 15, 2025, marking the final session for retiring Utility Superintendent...
lake land college.3

Board Reviews Proposed Tax Levy with Slight Increase Expected

Lake Land College Board of Trustees Meeting | November 2025 Article Summary: Lake Land College administrators presented a proposed aggregate tax levy for 2025 that includes a marginal increase over...
Clark County Graphic.5

County Freezes Employee Health Insurance Costs for FY 2026

Clark County Board Regular Meeting | November 2025 Article Summary: To maintain stability for county employees, the board voted to freeze the current cost of family health insurance plans and...
Screenshot 2025-12-24 at 1.11.08 PM

Police Department Adds New Officer, Introduces Another

Casey City Council Meeting | December 15, 2025 Article Summary: The City Council approved the hiring of Daniel Martinez to fill the police department's ninth position and formally welcomed recently...
Meeting Briefs

Meeting Summary and Briefs: Casey Township Library Board for Nov. 2025

Casey Township Library Board Meeting | Nov. 2025 The Casey Township Library Board convened twice in November 2025 to manage regular business and advance a major building expansion project. During...
lake land college.4

Lake Land College Board Awards $2.5 Million Contract for Front Entrance Improvements

Lake Land College Board of Trustees Meeting | November 2025 Article Summary: The Lake Land College Board of Trustees approved a multi-million dollar contract to overhaul the campus entrances, including...
Clark County Graphic.4

County Board Approves Proposal for New Rural-Focused Ambulance Support

Clark County Board Regular Meeting | November 2025 Article Summary: The Clark County Board authorized a proposal from H&H EMS Solutions to provide support services for the county's ambulance operations,...
Meeting Briefs

Meeting Summary and Briefs: Casey-Westfield CUSD C-4 Board for December 15, 2025

Casey-Westfield CUSD C-4 Board Meeting | December 15, 2025 The Casey-Westfield Community Unit School District C-4 Board of Education met on Monday, December 15, 2025, to address financial planning and...